Project Update - December 2019 

  • 100 Percent design plans are complete
  • Environmental clearance was achieved in November 2019  
  • City issued Request of Release of Funds to HUD in November 2019 and received Authority to Use Grant Funds in November 2019
  • Construction anticipated Spring/Summer 2020 pending ROW acquisition


Previous milestones

  • Preliminary Engineering Report (PER) completed March 2018 
  • Neighborhood meeting at Calvary Baptist Church June 11, 2018
  • Sand and Gravel Permit approved in October 2019 from Texas Parks and Wildlife Department
  • US Army Corp of Engineers Section 404 Permit received in October 2019