Project Update - August 2020 

  • 100 Percent design plans are complete.
  • Environmental clearance was achieved in November 2019  
  • City issued Request of Release of Funds to HUD in November 2019 and received Authority to Use Grant Funds in November 2019.
  • City currently acquiring easements and right-of-way
  • Construction anticipated in late 2020 pending ROW acquisition

Previous milestones:

  • Preliminary Engineering Report (PER) completed March 2018. 
  • Neighborhood meeting at Calvary Baptist Church June 112018.
  • Sand and Gravel Permit approved in October 2019 from Texas Parks and Wildlife Department
  • US Army Corp of Engineers Section 404 Permit received in October 2019