- Public Meeting - Environmental Document - held February 6, 2020
- Completed Preliminary Engineering Report
- 60% Final Design Completed
- 90% Final Design In-Progress
- Completed Engineering Feasibility Report and submitted to Texas Water Development Board
- Completed Environmental Information Document and submitted to Texas Water Development Board
- Environmental Assessment and Request for Release of Funds (RROF) approved by HUD
- Acquisition Process is In-Progress
On September 12, 2018, the second Blanco Riverine Flood Mitigation community meeting was held at the San Marcos Activity Center. Below are links to the presentation given at the meeting, in English and Spanish:
September 12 Community Meeting Presentation - English (PDF)
September 12 Community Meeting Presentation - Spanish (PDF)
- Design and Land Acquisition: Fall 2019 to Spring 2021
- Construction: to be determined
Budget: $23 million
Current Funding:
- TWDB = $1,961,821
- CDBG-DR (2017) = $5,385,213
- City (2019) = $2,628,800
Project Manager: Jacque Thomas
For more information on this, or any other City Project, email Engineering Information.