Upcoming Projects

Proposed Streets Projects

  • March 1, 2023- Heritage Neighborhood, Mill & Overlay
  • April 1, 2023- Riverwalk Lp, Riverwalk Dr., Cotter Ave, Riverway Ave., E. River Ridge, Avalon, Cottonwood Creek Phase 1, Davis Ln., Slurry Seal
  • June 1, 2023- E. Centerpoint, Centerpoint Ct., Mill & Overlay
  • June 1, 2023- Hughson Dr., Mill and Overlay
  • July 1, 2023- William Pettus, Sealcoat

Proposed Sidewalk Projects

  • April 1, 2023- MLK to S. LBJ to Guadalupe St.
  • March 1, 2023- Warden to Thorpe Ln. to Aquarena Springs
  • May 1, 2023-  Lindsey to Mary to North St.
  • May 1, 2023-  Eastwood to Thorpe Ln. to Mill St.
  • April 1, 2023- Sturgeon to Mary Ln. to River Road
  • July 1, 2023- Clair to Sturgeon to Conway
  • April 1, 2023- Second St. to Mill St. to Seguin St.
  • April 1, 2023- Laredo St. to Staples Rd. to Juarez St.
  • April 1, 2023- First St. to Mill St. to Lockhart
  • July 1, 2023- Conway to River Rd. to Bugg Ln.