Project Description:
In 2018 a feasibility study of drainage improvements to the Wallace Addition Neighborhood was initiated to identify improvements required to mitigate flooding within the subdivision. As a result of this study, it was determined that the existing Cape Road channel and the Staples Road ditch and associated culverts do not have adequate capacity to convey stormwater from a 25-year storm event.
The proposed project will include Cape Road Channel improvements and up-sizing the existing culvert, diverting the Staples Road ditch drainage via a proposed culvert under Staples Road and a channel along the Fish Hatchery property. The proposed improvements will alleviate surface runoff and localized flooding issues currently experienced in the neighborhood.
Project Schedule:
Design Completion: March 2022
Bidding: August 2022
Construction Completion: September 2023