Old RR12 Bike / Pedestrian & Widening

2017 - Project delayed at the request of City Council to make funds available for needed drainage projects

2018 – Design Plans Completed

2020-2022 – Project is on hold until the completion of Hopkins Street Improvements Project

Hopkins Street Improvements Project is using Old RR 12 as a major detour; both projects cannot be under construction at the same time

Construction is expected to be completed in late 2022

Hopkins Street Improvements Project Web page: Hopkins St Improvements - Bishop to Moore

Start Construction - 2023

End Construction - 2025

Project Cost - $6.6 M

Project Limits

Old Ranch Road 12 from Craddock to Holland, and 33 feet of Sarah Street

  • 3 Lanes total: One lane in each direction and a continuous center turn lane
  • Bike Lanes within the project limits
  • Drainage Improvements
  • Sidewalks on both sides of the road
  • Wastewater line and Eliminate 2 Lift Stations
  • Water line
  • Water Quality / LID features
  • Widening road from Craddock to Holland
RR 12 -Scope Exhibit