Project Update - May 2020

Storage tank is complete

  • Chlorinator building, fencing and gate are complete
  • Disinfection and pressure testing of lines is continuing 
  • Electrical and utility pole installation for the power feed is underway
  • A gravel driving surface for tank access will be installed prior to final completion
  • Final completion of the Elevated Storage Tank project scheduled for July 2020

Pump Station Improvements Project

  • Underground electric transfer for power feed complete
  • Variable Frequency Drives delivered
  • Pump upgrades to start in June, 2020
  • System acceptance testing in September, 2020