Project Update - August 2020

Storage tank is complete

  • Contractor is working on final punch list items

Pump Station Improvements Project

  • All three pumps have been removed and replaced
  • Final paint coating is being applied 
  • System acceptance testing in September, 2020

If you would like to receive project updates by email please send your email address to: enginfo@sanmarcostx.gov