Kingwood Street and Sherwood Drive are located in southwest San Marcos and connect to the TxDOT IH 35 frontage road. They are within the Willow Springs Creek watershed. The project will reconstruct both streets, upgrade the existing water and wastewater systems, and construct a new street drainage system. The project will also evaluate sidewalks and stormwater quality treatment facilities.
The project will be conducted in the following phases:
Design Phase 1 -
Started February 2020 - including topographic surveys
Preliminary Engineering Report (Draft) Submitted September 2020
Finalize Preliminary Engineering Report – October 2020
Design Phase 2 –
Continue Designs – 2021
Public Meeting – Early 2021
Complete Designs - 2022
Schedule and Budget
Construction start - Early 2023
Design - $400,000
Construction - $2,500,000