- This project includes upgrades to existing water and wastewater infrastructure by improving fire protection, hydraulics and overall capacity.
- Approximately 9,300 linear feet of the subdivision's existing waterlines and sanitary sewer system needs replacement due to aging infrastructure and known deficiencies.
- The project is currently in the preliminary design phase, with a feasibility report currently being developed. Topographic survey and geotechnical field work is complete in preparation of preliminary engineering.
Construction Start – 2023
Construction Estimate - $4.6M