  • Sidewalk & drainage completed on south side of Hopkins between Charles Austin and Thorpe Contractors shifted the sidewalk so drainage could be captured and re-routed under the sidewalk 
  • Sidewalk & drainage started on north side of Hopkins between Charles Austin and Thorpe