Uhland Road Improvements

Current Update: 04/2021

Work Completed Last Month: Phase 1 (of 4) work includes – approximately 60% of storm water sewer installed. Headwall structures for two new outfalls constructed. Inlets and junction boxes started for storm water. Approximately 40% of waterline work complete in Phase 1. Work on telephone poles to be relocated along Uhland Road started. 

Work Planned This Month: Continue stormwater construction. Start on road construction. Telecom firms will relocate fiber optic. Old telephone poles to be removed. Waterline work continues. 

Construction Completion: See Dashboard For Details

Pictures from last month
Pavement removal in Uhland-River Intersection3Storm pipe stored on River rdView SE on Uhland towards low water crossing